Step 8 of 13: Parameter Mapping Option 1: Map a CAD Model Parameter Directly

EL4.8: Direct link to a CAD Parameter within an Assembly

Written by Alexandra Göttert

The steps use the rail bracket examples from the EL4 training models; you can apply them to your own CAD models in the same way.

Understand how the example model is driven. In the first rail bracket, the bracket size is controlled by a sketch inside the assembly. The goal is to drive CAD parameter via the Liftdesigner Run Automation function so the original model adapts to the elevator project.

DP-SW RB01 0000 00.SLDASM

Expected Result

Prerequisites

  • Write protection is removed, and you know that a sketch inside the assembly controls the bracket size.

  • The rail bracket example model is loaded and positioned in the prepared Liftdesigner training project.

Steps

1.) Open the Assign Automation dialog. Select the CAD model and click Assign in the Automation ribbon group. Assign mappings directly to your CAD model parameter by selecting the associated Mapping column.

2.) Add an assignment record and choose the target CAD parameter. Add a new assignment record and choose the CAD parameter from the Target CAD Parameter list. The list shows CAD parameters that control sketches, features, and/or equations. After you add the record, the CAD model opens automatically in the corresponding CAD application.

3.) Choose the Liftdesigner source value. Choose the DigiPara Liftdesigner source value to link with from the PG-Parameter list. The list contains the usable DigiPara Liftdesigner rail bracket parameters — similar to the [0520] 3D Parameter group in the CAD model's properties window.

4.) Change the source value and run the automation. Change the linked Liftdesigner source value in the current project, select the CAD model, and click Run Automation.

Result

The CAD model parameter is driven directly by a DigiPara Liftdesigner parameter: when the project value changes and you run the automation, the original CAD model adapts to the elevator project.